Waste-to-Energy Projects
Linyi, Shandong Province
Linyi, Shandong waste treatment plant overview
- The waste to energy plant uses Circulating Fluidized bed (CFB) technology.
- HKC owns 40%, in joint venture with CECIC
- Total investment cost: RMB 237 million
- Installed capacity of #25 MW co-generation plant will be able to generate upto 120 million kWh of electricity annually.
- Annual garbage treatment capacity: 300,000 tons
- Commissioned in Sept 2007
- Diverse revenue streams:
- Garbage processing fee
- Electricity tariff
- CDM credits
- Ash
- Exclusive right to build Phase II as the city expands and population grows in the near future
|
|
 |
 |